Works:
General design and General contract
Duration:
II qtr. 2008 III qtr. 2009
Size:
56 000 2

Works:
Erection of assembled RCC and metal structures of the building
Duration:
II qtr. 2007 III qtr. 2007
Size:
30,000 m2

Projects Archive

History

Company "MONKON" is based in 1992 by experts of former Minmontazhspetsstroja of the USSR who have brought in again created organisation the richest experience of building of difficult and unique objects, innovative decisions in process of performance of works, the best operating time in the field of management of building manufacture.


1992

- the shop on manufacture of sausages “Tsaritsynskiy Meat-processing Plant” is constructed


1993

- works on strengthening of bearing designs of a building of Kurskiy Railway Station are finished


1995

- restoration works of an administrative building LUKOIL are spent


1996

- the landing-stage a building of the Kievskiy Railway Station is made and mounted


1997

- reconstruction of a roof of an office building of the Bank Alba Alliance is executed
- the shopping complex near the Tsarytsino station, Moscow is constructed
- reconstruction of stained-glass windows of the main building of the Belarusskiy Railway Station is executed


1998

- the pedestrian-transport overpass of Central Clinical Hospital of Moscow is made and mounted


1999

- 12 pedestrian bridges on Rublevsky highway, by Leninsk and Ryazan prospectuses, Moscow are made and mounted
- vegetable storehouse building on 3000 tons in settlement Bunjatino, to Dmitrovsky r thow Moscow Region is finished


2000

- the process plant Ice-Fili is constructed
- blank warehouse of the plant Serp I Molot is constructed
- the shopping complex with underground parking at Sokolnicheskaya Square, Moscow is erected
- the device of a monolithic skeleton 9 storied individual residential house on 2nd Kvesissky street, Moscow is executed


2001

- are made and mounted metal designs filling station complexes British Petroleum
- works on building of the entertainment center on Profsoyuznaya Street, Moscow are finished
- are made and mounted metal designs of summer theatre in park Troparevo, Moscow


2002

- are made and mounted 3000 tone metal designs 24 storied residential house on Ivankovsky highway, Moscow
- are made and mounted designs not passing noise on crossing of the Kutuzovsky prospectus and the Third Transport Ring, Moscow
- reconstruction of the block 10, thermal power station-11, Moscow is made
- the mansard floor of building Municipal Department of Internal Affairs, Moscow is erected


2003

- the project of a trading-cultural complex in settlement Zhukovka, Moscow Region is realised
- are made and mounted metal designs glass production plant building Glaverbel-Klin
- decking of pedestrian subway on crossing of street Trofimova and the Third Transport Ring, Moscow are made and mounted


2004

- are made and mounted metal designs buildings, and also are mountedinfilling panels of a supermarket "Perekrestok" in settlement Gorki-2 of Moscow Region
- are made and mounted metal designs buildings of a city airport Anadyr


2005

- are made and mounted metal designs a dispatching tower, the main facade of the basic building, and also sites of a landing zone of international airport "Domodedovo"
- works are performed on manufacturing and installation metal designs buildings, and also to installation infilling panels of a warehouse complex of factory MEVZ on the Varshavskoye highway, Moscow
- installation of modular ferro-concrete and metal designs of the warehouse terminal «Belaya Dacha-2» is executed


2006

- installation of modular ferro-concrete and metal designs of factory on processing of fresh salads and vegetables Company Belaya Dacha is executed
- are made and mounted metal designs buildings, and also are mounted infilling panels of a hypermarket Mosmart on crossing of Bohr highway and MKAD
- are made and mounted metal designs a cold storage Agama Logistic Istra
- installation of modular ferro-concrete and metal designs of the warehouse terminal Belaya Dacha-4 is executed


2007

- are made and mounted metal designs the sports-youth center "Roshal"
- are made and mounted metal designs buildings of anglo-american school on Ivankovsky highway, Moscow
- are made and mounted metal designs shopping centre MEGA-Dacha-Ashan
- the industrial-warehouseCompany Russian Pole - logistik 2 turn is constructed
- installation of modular ferro-concrete and metal designs of the warehouse terminal Belaya Dacha-3 is executed
- are made and mounted metal designs shopping-office center Shuka


2008

- the cold-storage KPD Terminal is constructed
- are made and mounted metal designs buildings, and also are mounted infilling panels of a warehouse complexcompany Enter Logistica
- are made and mounted metal designs buildings of logistical terminal "" to Tver


2009

- the civil-engineering design of a five-temperature warehouse complex "Agroterminal" is realised


2010

- works on manufacturing and installation of two electrofilters of industrial furnaces of cement works of "Voskpesenskcement" are conducted

- works on manufacturing and installation of metal designs of "Top-golf complex" in a sports complex "Luzniki" have begun